Requirement :
|
Bza division: gdr-bza section: sw-i) ctr(p): complete track renewal of existing 52kg/60kg/90uts rails on psc5 sleepers (m+7)/(m+4) density with new 60kg/90uts rails (lwr) on new psc6 sleepers1660 nos./km on up and down lines for a total length of 32.114km in aden/bapatla sub-division. (ctr(p) with pqrs for a length of 27.495km at vetapalem depot and ctr(p) by manual for a length of 4.619km ) sw-ii) gdr-bza section.-trr(p): through rail renewal of existing 52kg/60kg(90uts) rails on psc6 sleepers 1660 density with new 60kg/90uts rails ( lwr) on up and down lines for a total length of 33.808km in aden/bapatla sub-division. sw-iii) : bza-vskp section: trr(p): through rail renewal of existing 60kg(90uts) rails on psc6 sleepers 1660 density with new 60kg/90uts rails ( lwr) on up & down lines for a total length of 1.964km in aden/eluru sub-division.
|